May
At Someșului 15, construction progress is steadily turning the project’s vision into an increasingly visible reality.
The reinforced concrete structure has been fully completed (100%), and masonry work is fully finished from the 1st to the 5th floor, while at ground floor level the works are 90% complete.
Inside, finishing works are progressing steadily: plastering on the 6th floor is 50% complete, while skim coat (gypsum finishing) works have reached 70% on the 1st floor, 50% on the 2nd floor, 30% on the 3rd floor, and 15% on the 4th floor. Drywall partitions are 50% complete on floors 1, 2, and 3, and 10% complete on the 4th floor.
The REHAU BKT ceiling heating and cooling system has been fully installed (100%) from the 1st to the 6th floor. Electrical installations are completed up to the 5th floor and 50% completed on the 6th floor, while plumbing installations and technical shafts are also completed up to the 5th floor and 50% executed on the top level.
On the exterior, the building is beginning to take on its final appearance: windows are 90% installed, balcony waterproofing has reached 95%, terrace waterproofing is 50% complete, and the ventilated façade is 35% finished.
Someșului 15 is taking shape in central Cluj, combining contemporary architecture, energy efficiency, and a rare location near the Someș River.
May
At Someșului 15, construction progress is steadily turning the project’s vision into an increasingly visible reality.
The reinforced concrete structure has been fully completed (100%), and masonry work is fully finished from the 1st to the 5th floor, while at ground floor level the works are 90% complete.
Inside, finishing works are progressing steadily: plastering on the 6th floor is 50% complete, while skim coat (gypsum finishing) works have reached 70% on the 1st floor, 50% on the 2nd floor, 30% on the 3rd floor, and 15% on the 4th floor. Drywall partitions are 50% complete on floors 1, 2, and 3, and 10% complete on the 4th floor.
The REHAU BKT ceiling heating and cooling system has been fully installed (100%) from the 1st to the 6th floor. Electrical installations are completed up to the 5th floor and 50% completed on the 6th floor, while plumbing installations and technical shafts are also completed up to the 5th floor and 50% executed on the top level.
On the exterior, the building is beginning to take on its final appearance: windows are 90% installed, balcony waterproofing has reached 95%, terrace waterproofing is 50% complete, and the ventilated façade is 35% finished.
Someșului 15 is taking shape in central Cluj, combining contemporary architecture, energy efficiency, and a rare location near the Someș River.

March
The structure is completed at the upper levels, and the masonry work is fully executed up to the 5th floor and continues on the 6th floor. Inside, plastering is completed up to the 4th floor, while electrical and plumbing installations are carried out up to the 5th floor, and skim coating has begun on the lower levels.
The heating and cooling system integrated into the ceilings has already been implemented on the upper floors.
In parallel, finishing works are beginning to shape the final appearance: window frames are being installed, waterproofing works are being carried out, and the ventilated façade is taking shape.
The project is progressing steadily, and each stage brings Someșului 15 closer to its final form.
March
The structure is completed at the upper levels, and the masonry work is fully executed up to the 5th floor and continues on the 6th floor. Inside, plastering is completed up to the 4th floor, while electrical and plumbing installations are carried out up to the 5th floor, and skim coating has begun on the lower levels.
The heating and cooling system integrated into the ceilings has already been implemented on the upper floors.
In parallel, finishing works are beginning to shape the final appearance: window frames are being installed, waterproofing works are being carried out, and the ventilated façade is taking shape.
The project is progressing steadily, and each stage brings Someșului 15 closer to its final form.

February
- Slab above Level E6S – 100%
- Vertical elements – E6S – 50%
- Terrace slab – 50%
- Ground floor masonry – 90%
- Masonry E1 – 100%
- Masonry E2 – 100%
- Masonry E3 – 100%
- Masonry E4 – 100%
- Masonry E5 – 100%
- Masonry E6 – 30%
- Plastering E1 – 100%
- Plastering E2 – 100%
- Plastering E3 – 60%
- Heating & cooling system (BKT) E6 – 100%
- Heating & cooling system (BKT) E6S – 50%
- Electrical installations in apartments E1 – 100%
- Electrical installations in apartments E2 – 100%
- Electrical installations in apartments E3 – 100%
- Electrical installations in apartments E4 – 60%
- Sanitary installations + service shafts E3 – 100%
- Sanitary installations + service shafts E4 – 100%
- Sanitary installations + service shafts E5 – 100%
February
- Slab above Level E6S – 100%
- Vertical elements – E6S – 50%
- Terrace slab – 50%
- Ground floor masonry – 90%
- Masonry E1 – 100%
- Masonry E2 – 100%
- Masonry E3 – 100%
- Masonry E4 – 100%
- Masonry E5 – 100%
- Masonry E6 – 30%
- Plastering E1 – 100%
- Plastering E2 – 100%
- Plastering E3 – 60%
- Heating & cooling system (BKT) E6 – 100%
- Heating & cooling system (BKT) E6S – 50%
- Electrical installations in apartments E1 – 100%
- Electrical installations in apartments E2 – 100%
- Electrical installations in apartments E3 – 100%
- Electrical installations in apartments E4 – 60%
- Sanitary installations + service shafts E3 – 100%
- Sanitary installations + service shafts E4 – 100%
- Sanitary installations + service shafts E5 – 100%

January
- Slab above Level E5 – 100%
- Vertical elements – E6 – 80%
- Slab above Level E6 – 50%
- Ground floor masonry – 90%
- Masonry E1 – 100%
- Masonry E2 – 100%
- Masonry E3 – 100%
- Masonry E4 – 80%
- Masonry E5 – 10%
- Plastering E1 – 100%
- Plastering E2 – 60%
- Heating & cooling system (BKT) E5 – 100%
- Heating & cooling system (BKT) E6 – 50%
- Electrical installations in apartments E1 – 100%
- Electrical installations in apartments E2 – 100%
- Electrical installations in apartments E3 – 50%
- Sanitary installations + service shafts E1 – 100%
- Sanitary installations + service shafts E2 – 100%
- Sanitary installations + service shafts E3 – 80%
January
- Slab above Level E5 – 100%
- Vertical elements – E6 – 80%
- Slab above Level E6 – 50%
- Ground floor masonry – 90%
- Masonry E1 – 100%
- Masonry E2 – 100%
- Masonry E3 – 100%
- Masonry E4 – 80%
- Masonry E5 – 10%
- Plastering E1 – 100%
- Plastering E2 – 60%
- Heating & cooling system (BKT) E5 – 100%
- Heating & cooling system (BKT) E6 – 50%
- Electrical installations in apartments E1 – 100%
- Electrical installations in apartments E2 – 100%
- Electrical installations in apartments E3 – 50%
- Sanitary installations + service shafts E1 – 100%
- Sanitary installations + service shafts E2 – 100%
- Sanitary installations + service shafts E3 – 80%