November
- Slab above Level E4 – 100%
- Vertical elements – E5 – 100%
- Slab above Level E5 – 50%
- Ground floor masonry – 60%
- Masonry E1 – 100%
- Masonry E2 – 100%
- Masonry E3 – 80%
- Plastering E1 – 60%
- Heating & cooling system (BKT) E4 – 100%
- Heating & cooling system (BKT) E5 – 50%
- Electrical installations in concrete elements E4 – 100%
- Electrical installations in concrete elements E5 – 100%
November
- Slab above Level E4 – 100%
- Vertical elements – E5 – 100%
- Slab above Level E5 – 50%
- Ground floor masonry – 60%
- Masonry E1 – 100%
- Masonry E2 – 100%
- Masonry E3 – 80%
- Plastering E1 – 60%
- Heating & cooling system (BKT) E4 – 100%
- Heating & cooling system (BKT) E5 – 50%
- Electrical installations in concrete elements E4 – 100%
- Electrical installations in concrete elements E5 – 100%

October
- Reinforcement and casting of slab above Floor 3 – 100%
- Execution of vertical elements – Floor 4 – 100%
- Reinforcement and casting of slab above Floor 4 – 50%
- Ground floor masonry – 60%
- Masonry Floor 1 – 100%
- Masonry Floor 2 – 30%
- Heating & cooling system (BKT) Floor 3 – 100%
- Heating & cooling system (BKT) Floor 4 – 50%
- Electrical installations in concrete elements Floor 3 – 100%
- Electrical installations in concrete elements Floor 4 – 100%
October
- Reinforcement and casting of slab above Floor 3 – 100%
- Execution of vertical elements – Floor 4 – 100%
- Reinforcement and casting of slab above Floor 4 – 50%
- Ground floor masonry – 60%
- Masonry Floor 1 – 100%
- Masonry Floor 2 – 30%
- Heating & cooling system (BKT) Floor 3 – 100%
- Heating & cooling system (BKT) Floor 4 – 50%
- Electrical installations in concrete elements Floor 3 – 100%
- Electrical installations in concrete elements Floor 4 – 100%

September
- Slab above Level E2 – 100%
- Vertical elements E3 – 100%
- Slab above Level E3 – 50%
- Ground floor masonry – 25%
- Heating & cooling system (BKT) E2 – 100%
- Heating & cooling system (BKT) E3 – 50%
- Electrical installations in concrete elements E2 – 100%
- Electrical installations in concrete elements E3 – 50%
September
- Slab above Level E2 – 100%
- Vertical elements E3 – 100%
- Slab above Level E3 – 50%
- Ground floor masonry – 25%
- Heating & cooling system (BKT) E2 – 100%
- Heating & cooling system (BKT) E3 – 50%
- Electrical installations in concrete elements E2 – 100%
- Electrical installations in concrete elements E3 – 50%





August
- Ground floor reinforced concrete vertical elements – 100%
- Slab above ground floor – 100%
- Vertical elements E1 – 100%
- Slab above E1 – 100%
- Vertical elements E2 – 20%
- Heating & cooling system Rehau BKT E1 – 100%
- Electrical installations in concrete elements P+E1 – 100%
- Backfilling works – 90%
August
- Ground floor reinforced concrete vertical elements – 100%
- Slab above ground floor – 100%
- Vertical elements E1 – 100%
- Slab above E1 – 100%
- Vertical elements E2 – 20%
- Heating & cooling system Rehau BKT E1 – 100%
- Electrical installations in concrete elements P+E1 – 100%
- Backfilling works – 90%







July
Residential building
- Execution of reinforced concrete vertical elements – Ground floor – 90%
- Reinforcement and casting of slab above ground floor – 90%
- Electrical installations embedded in concrete elements E1 – 30%
- Reinforcement and casting of vertical elements E1 – 30%
- Integration of geothermal energy recovery system (Tichelmann loop)
- Raft foundation support – Phase 3
- Raft reinforcement – Phase 3
July
Residential building
- Execution of reinforced concrete vertical elements – Ground floor – 90%
- Reinforcement and casting of slab above ground floor – 90%
- Electrical installations embedded in concrete elements E1 – 30%
- Reinforcement and casting of vertical elements E1 – 30%
- Integration of geothermal energy recovery system (Tichelmann loop)
- Raft foundation support – Phase 3
- Raft reinforcement – Phase 3
June
Residential building
- Execution of reinforced concrete vertical elements S1 – 100%
- Reinforcement and casting of slab above S1 – 100%
- Electrical installations (lighting, fire detection & alarm) in vertical elements S1 – 100%
- Reinforcement and casting of ground floor vertical elements – 50%
June
Residential building
- Execution of reinforced concrete vertical elements S1 – 100%
- Reinforcement and casting of slab above S1 – 100%
- Electrical installations (lighting, fire detection & alarm) in vertical elements S1 – 100%
- Reinforcement and casting of ground floor vertical elements – 50%
May
Residential building
- Execution of reinforced concrete vertical elements S2 – 70%
- Casting of slab above S2 – 50%
- Vertical elements S1 – 10%
- Electrical installations (lighting, fire detection & alarm) in vertical elements S2 – 70%
- Electrical installations (lighting, fire detection & alarm) in slab above S2 – 70%
- Drainage installations for accidental water (slab above S2) – 50%
- Installation of Pentaflex waterproofing elements in walls and slabs
May
Residential building
- Execution of reinforced concrete vertical elements S2 – 70%
- Casting of slab above S2 – 50%
- Vertical elements S1 – 10%
- Electrical installations (lighting, fire detection & alarm) in vertical elements S2 – 70%
- Electrical installations (lighting, fire detection & alarm) in slab above S2 – 70%
- Drainage installations for accidental water (slab above S2) – 50%
- Installation of Pentaflex waterproofing elements in walls and slabs
April
- Raft foundation concrete casting (building foundation)
- Raft reinforcement (building foundation)
- Geothermal energy installations
- Retaining structure support with steel struts
- Basement water collection system
- Waterproof concrete joint executed with Pentaflex ABS profile
- Geothermal energy installations
- Waterproofing solutions with Pentaflex ABS joint profiles + Pentaflex metal sheets
- Geothermal energy pipe loops
April
- Raft foundation concrete casting (building foundation)
- Raft reinforcement (building foundation)
- Geothermal energy installations
- Retaining structure support with steel struts
- Basement water collection system
- Waterproof concrete joint executed with Pentaflex ABS profile
- Geothermal energy installations
- Waterproofing solutions with Pentaflex ABS joint profiles + Pentaflex metal sheets
- Geothermal energy pipe loops
January
Retaining structure:
- Perimeter piles (retaining structure) – 100%
- Geothermal energy system in retaining piles – 90%
- Perimeter beam – 100%
- Steel struts for retaining support – 100%
- Dewatering system – 100%
Infrastructure:
- Excavation – 90%
- Foundation piles – 100%
- Geothermal energy recovery system in foundation piles – 90%
- Geothermal energy recovery system under raft – 5%
January
Retaining structure:
- Perimeter piles (retaining structure) – 100%
- Geothermal energy system in retaining piles – 90%
- Perimeter beam – 100%
- Steel struts for retaining support – 100%
- Dewatering system – 100%
Infrastructure:
- Excavation – 90%
- Foundation piles – 100%
- Geothermal energy recovery system in foundation piles – 90%
- Geothermal energy recovery system under raft – 5%