HomepageLifestyle and LocationApartmentsCommercial spaces

Request an offer

Project evolution

November

  • Slab above Level E4 – 100%
  • Vertical elements – E5 – 100%
  • Slab above Level E5 – 50%
  • Ground floor masonry – 60%
  • Masonry E1 – 100%
  • Masonry E2 – 100%
  • Masonry E3 – 80%
  • Plastering E1 – 60%
  • Heating & cooling system (BKT) E4 – 100%
  • Heating & cooling system (BKT) E5 – 50%
  • Electrical installations in concrete elements E4 – 100%
  • Electrical installations in concrete elements E5 – 100%

November

  • Slab above Level E4 – 100%
  • Vertical elements – E5 – 100%
  • Slab above Level E5 – 50%
  • Ground floor masonry – 60%
  • Masonry E1 – 100%
  • Masonry E2 – 100%
  • Masonry E3 – 80%
  • Plastering E1 – 60%
  • Heating & cooling system (BKT) E4 – 100%
  • Heating & cooling system (BKT) E5 – 50%
  • Electrical installations in concrete elements E4 – 100%
  • Electrical installations in concrete elements E5 – 100%

October

  • Reinforcement and casting of slab above Floor 3 – 100%
  • Execution of vertical elements – Floor 4 – 100%
  • Reinforcement and casting of slab above Floor 4 – 50%
  • Ground floor masonry – 60%
  • Masonry Floor 1 – 100%
  • Masonry Floor 2 – 30%
  • Heating & cooling system (BKT) Floor 3 – 100%
  • Heating & cooling system (BKT) Floor 4 – 50%
  • Electrical installations in concrete elements Floor 3 – 100%
  • Electrical installations in concrete elements Floor 4 – 100%

October

  • Reinforcement and casting of slab above Floor 3 – 100%
  • Execution of vertical elements – Floor 4 – 100%
  • Reinforcement and casting of slab above Floor 4 – 50%
  • Ground floor masonry – 60%
  • Masonry Floor 1 – 100%
  • Masonry Floor 2 – 30%
  • Heating & cooling system (BKT) Floor 3 – 100%
  • Heating & cooling system (BKT) Floor 4 – 50%
  • Electrical installations in concrete elements Floor 3 – 100%
  • Electrical installations in concrete elements Floor 4 – 100%

September

  • Slab above Level E2 – 100%
  • Vertical elements E3 – 100%
  • Slab above Level E3 – 50%
  • Ground floor masonry – 25%
  • Heating & cooling system (BKT) E2 – 100%
  • Heating & cooling system (BKT) E3 – 50%
  • Electrical installations in concrete elements E2 – 100%
  • Electrical installations in concrete elements E3 – 50%

September

  • Slab above Level E2 – 100%
  • Vertical elements E3 – 100%
  • Slab above Level E3 – 50%
  • Ground floor masonry – 25%
  • Heating & cooling system (BKT) E2 – 100%
  • Heating & cooling system (BKT) E3 – 50%
  • Electrical installations in concrete elements E2 – 100%
  • Electrical installations in concrete elements E3 – 50%

August

  • Ground floor reinforced concrete vertical elements – 100%
  • Slab above ground floor – 100%
  • Vertical elements E1 – 100%
  • Slab above E1 – 100%
  • Vertical elements E2 – 20%
  • Heating & cooling system Rehau BKT E1 – 100%
  • Electrical installations in concrete elements P+E1 – 100%
  • Backfilling works – 90%

August

  • Ground floor reinforced concrete vertical elements – 100%
  • Slab above ground floor – 100%
  • Vertical elements E1 – 100%
  • Slab above E1 – 100%
  • Vertical elements E2 – 20%
  • Heating & cooling system Rehau BKT E1 – 100%
  • Electrical installations in concrete elements P+E1 – 100%
  • Backfilling works – 90%

July

Residential building
  • Execution of reinforced concrete vertical elements – Ground floor – 90%
  • Reinforcement and casting of slab above ground floor – 90%
  • Electrical installations embedded in concrete elements E1 – 30%
  • Reinforcement and casting of vertical elements E1 – 30%
  • Integration of geothermal energy recovery system (Tichelmann loop)
  • Raft foundation support – Phase 3
  • Raft reinforcement – Phase 3

July

Residential building
  • Execution of reinforced concrete vertical elements – Ground floor – 90%
  • Reinforcement and casting of slab above ground floor – 90%
  • Electrical installations embedded in concrete elements E1 – 30%
  • Reinforcement and casting of vertical elements E1 – 30%
  • Integration of geothermal energy recovery system (Tichelmann loop)
  • Raft foundation support – Phase 3
  • Raft reinforcement – Phase 3

June

Residential building
  • Execution of reinforced concrete vertical elements S1 – 100%
  • Reinforcement and casting of slab above S1 – 100%
  • Electrical installations (lighting, fire detection & alarm) in vertical elements S1 – 100%
  • Reinforcement and casting of ground floor vertical elements – 50%

June

Residential building
  • Execution of reinforced concrete vertical elements S1 – 100%
  • Reinforcement and casting of slab above S1 – 100%
  • Electrical installations (lighting, fire detection & alarm) in vertical elements S1 – 100%
  • Reinforcement and casting of ground floor vertical elements – 50%

May

Residential building
  • Execution of reinforced concrete vertical elements S2 – 70%
  • Casting of slab above S2 – 50%
  • Vertical elements S1 – 10%
  • Electrical installations (lighting, fire detection & alarm) in vertical elements S2 – 70%
  • Electrical installations (lighting, fire detection & alarm) in slab above S2 – 70%
  • Drainage installations for accidental water (slab above S2) – 50%
  • Installation of Pentaflex waterproofing elements in walls and slabs

May

Residential building
  • Execution of reinforced concrete vertical elements S2 – 70%
  • Casting of slab above S2 – 50%
  • Vertical elements S1 – 10%
  • Electrical installations (lighting, fire detection & alarm) in vertical elements S2 – 70%
  • Electrical installations (lighting, fire detection & alarm) in slab above S2 – 70%
  • Drainage installations for accidental water (slab above S2) – 50%
  • Installation of Pentaflex waterproofing elements in walls and slabs

April

  • Raft foundation concrete casting (building foundation)
  • Raft reinforcement (building foundation)
  • Geothermal energy installations
  • Retaining structure support with steel struts
  • Basement water collection system
  • Waterproof concrete joint executed with Pentaflex ABS profile
  • Geothermal energy installations
  • Waterproofing solutions with Pentaflex ABS joint profiles + Pentaflex metal sheets
  • Geothermal energy pipe loops

April

  • Raft foundation concrete casting (building foundation)
  • Raft reinforcement (building foundation)
  • Geothermal energy installations
  • Retaining structure support with steel struts
  • Basement water collection system
  • Waterproof concrete joint executed with Pentaflex ABS profile
  • Geothermal energy installations
  • Waterproofing solutions with Pentaflex ABS joint profiles + Pentaflex metal sheets
  • Geothermal energy pipe loops

January

Retaining structure:
  • Perimeter piles (retaining structure) – 100%
  • Geothermal energy system in retaining piles – 90%
  • Perimeter beam – 100%
  • Steel struts for retaining support – 100%
  • Dewatering system – 100%
Infrastructure:
  • Excavation – 90%
  • Foundation piles – 100%
  • Geothermal energy recovery system in foundation piles – 90%
  • Geothermal energy recovery system under raft – 5%

January

Retaining structure:
  • Perimeter piles (retaining structure) – 100%
  • Geothermal energy system in retaining piles – 90%
  • Perimeter beam – 100%
  • Steel struts for retaining support – 100%
  • Dewatering system – 100%
Infrastructure:
  • Excavation – 90%
  • Foundation piles – 100%
  • Geothermal energy recovery system in foundation piles – 90%
  • Geothermal energy recovery system under raft – 5%

Learn more about the project

Footer logo
CallSee the apartments

Request an offer

Call0371781002Whatsapp